Question
Download Solution PDFThe rainfall observed for five successive days in a catchment is 2, 3, 4, 5 and 6 cm. Compute the direct runoff from the catchment due to this rainfall. The ϕ index for the rainfall is assumed to be 2 cm/day.
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFConcept:
Runoff depth generated for a given period is given as
R = P - ϕ if P ≥ ϕ
R = 0 if P < ϕ Where,
P is the rainfall and
ϕ is the infiltration loss in that given period.
Calculation:
Rainfall,p | time(days) | ϕ-Index(cm/day) | Runoff,R(cm) | Remark |
2 | 1 | 2 | 0 | p < ϕ |
3 | 1 | 2 | 1 | p > ϕ |
4 | 1 | 2 | 2 | p > ϕ |
5 | 1 | 2 | 3 | p > ϕ |
6 | 1 | 2 | 4 | p > ϕ |
It is clear that runoff is the summation of above runoffs per day
which is 10cm (Ans)
Last updated on Jul 1, 2025
-> SSC JE notification 2025 for Civil Engineering has been released on June 30.
-> Candidates can fill the SSC JE CE application from June 30 to July 21.
-> SSC JE Civil Engineering written exam (CBT-1) will be conducted on 21st to 31st October.
-> The selection process of the candidates for the SSC Junior Engineer post consists of Paper I, Paper II, Document Verification, and Medical Examination.
-> Candidates who will get selected will get a salary range between Rs. 35,400/- to Rs. 1,12,400/-.
-> Candidates must refer to the SSC JE Previous Year Papers and SSC JE Civil Mock Test, SSC JE Electrical Mock Test, and SSC JE Mechanical Mock Test to understand the type of questions coming in the examination.
-> The Staff Selection Commission conducts the SSC JE exam to recruit Junior Engineers in different disciplines under various departments of the Central Government.