Performance Management MCQ Quiz in मराठी - Objective Question with Answer for Performance Management - मोफत PDF डाउनलोड करा

Last updated on Apr 15, 2025

पाईये Performance Management उत्तरे आणि तपशीलवार उपायांसह एकाधिक निवड प्रश्न (MCQ क्विझ). हे मोफत डाउनलोड करा Performance Management एमसीक्यू क्विझ पीडीएफ आणि बँकिंग, एसएससी, रेल्वे, यूपीएससी, स्टेट पीएससी यासारख्या तुमच्या आगामी परीक्षांची तयारी करा.

Latest Performance Management MCQ Objective Questions

Top Performance Management MCQ Objective Questions

Performance Management Question 1:

Hurst Co budgeted to produce 16,000 units of a product and sell 15,000 units. There was no opening inventory. The standard cost per unit of the product is as follows:

  $
Direct materials 20
Direct labour 15
Variable production overheads 5
Fixed production overheads 10
  50
Standard selling price 80

Actual production was 18,500 units and 17,000 units were sold. Actual fixed production overheads were $165,000.

What was the fixed overhead expenditure variance for the period?

  1. $15,000 adverse
  2. $5,000 adverse
  3. $5,000 favourable
  4. $20,000 favourable

Answer (Detailed Solution Below)

Option 2 : $5,000 adverse

Performance Management Question 1 Detailed Solution

The correct option is option 2.

Additional information:

Budgeted fixed overhead expenditure = $10 × 16,000 = $160,000

Expenditure variance = Actual expenditure − budgeted expenditure = $165,000 − $160,000 = $5,000 adverse

Performance Management Question 2:

 Which of the following best describes “management by exception”?

  1. Using management reports to highlight exceptionally good performance, so that favourable results can be built upon to improve future outcomes
  2. Sending management reports only to those managers who are able to act on the information contained within the reports
  3. Focusing management reports on areas which require attention and ignoring those which appear to be performing within acceptable limits
  4. Appointing and promoting only exceptional managers to areas of responsibility within the organisation

Answer (Detailed Solution Below)

Option 3 : Focusing management reports on areas which require attention and ignoring those which appear to be performing within acceptable limits

Performance Management Question 2 Detailed Solution

The correct option is option 3.

Focusing management reports on areas which require attention and ignoring those which appear to be performing within acceptable limits

Performance Management Question 3:

The standard raw material cost for a unit of production is 2 kg at $4.00 per kg. Purchases for a period were 13,000 kg at an actual cost of $4.50 per kg. Raw material inventory, which is valued at standard cost, increased by $8,000 in the period. Budgeted production for the period was 6,000 units but actual production was only 5,000 units.

What was the raw material usage variance for the period?

  1. $4,000 adverse
  2. $4,000 favourable
  3. $12,000 adverse
  4. $12,000 favourable

Answer (Detailed Solution Below)

Option 1 : $4,000 adverse

Performance Management Question 3 Detailed Solution

The correct option is option 1.

WORKING

Actual production should have used 10,000 kg (5,000 × 2). Raw material inventory increased by 2,000 kg ($8,000/$4), so 11,000 kg of the 13,000 purchased went into production. The material usage variance is therefore (10,000 kg − 11,000 kg) × $4 = $4,000 Adverse.

Performance Management Question 4:

A manufacturing company operates a standard absorption costing system. Last month 25,000 production hours were budgeted and the budgeted fixed production overhead cost was $125,000. Last month the actual hours worked were 24,000 and the standard hours for actual production were 27,000.

What was the fixed production overhead capacity variance for last month?

  1. $5,000 adverse
  2. $5,000 favourable
  3. $10,000 adverse
  4. $10,000 favourable

Answer (Detailed Solution Below)

Option 1 : $5,000 adverse

Performance Management Question 4 Detailed Solution

The correct answer is A.

WORKING

Capacity variance:  
Actual hours 24,000
Budgeted hours 25,000
Under capacity (hours) 1,000
× standard overhead absorption rate (125,000/25,000) 5
Capacity variance (adverse) 5,000

 

The capacity variance is adverse because actual hours are less than budgeted hours, which may lead to less overheads being absorbed than expected and under-absorption (loss).

Performance Management Question 5:

Which one of the following is UNLIKELY to be the reason for an adverse material price variance?

 

  1. The budget incorporated an assumption of price inflation of 4% and the actual rate is 6%
  2. To reduce waste, a higher grade of material has been purchased
  3. A major supplier has introduced a discount scheme which had not been planned for
  4. An inexperienced purchase clerk ordered materials from four different suppliers

Answer (Detailed Solution Below)

Option 3 : A major supplier has introduced a discount scheme which had not been planned for

Performance Management Question 5 Detailed Solution

The correct option is option 3.

Additional information:

A discount scheme that has not been planned for – this would mean that actual price was less than expected, leading to a favourable price variance. All other options would most likely lead to an adverse price variance.

Performance Management Question 6:

The budgeted selling price of one of C’s range of chocolate bars was $6.00 per bar. At the beginning of the budget period market prices of cocoa increased significantly and C decided to increase the selling price of the chocolate bar by 10% for the whole period. C also decided to increase the amount spent on marketing and as a result actual sales volumes increased to 15,750 bars which was 5% above the budgeted volume. The standard contribution per bar was $2.00. However, a contribution of $2.25 per bar was actually achieved.

How much was the favourable sales volume contribution variance for the period

  1. $1,500
  2. $1,688
  3. $3,750
  4. $3,938

Answer (Detailed Solution Below)

Option 1 : $1,500

Performance Management Question 6 Detailed Solution

The correct option is option 1.

Additional information:

Sales volume contribution variance = (15,750 − 15,000) × $2.00 = $1,500 Favourable

Budgeted sales were 15,750/1.05 = 15,000 units

Performance Management Question 7:

Moony budgeted to make 50,000 units of its sole product, the koa. Fixed overheads are absorbed on the basis of $8 per hour for 2 labour hours.

The actual production of the koa was 52,000 units, which took 102,500 labour hours to manufacture. Total fixed overheads were $810,000.

What was the fixed overhead capacity variance?

  1. $10,000 adverse
  2. $12,000 favourable
  3. $20,000 favourable
  4. $32,000 favourable

Answer (Detailed Solution Below)

Option 3 : $20,000 favourable

Performance Management Question 7 Detailed Solution

The correct option is option 3.

  Hrs  
Actual labour hours 102,500  
Budgeted labour hours (50,000 × 2 hr) 100,000  
Difference 2,500  
  $  
× Standard rate per hour 8  
  20,000 Fav

 

Note: for the fixed overhead capacity variance, having more actual labour hours than budgeted leads to a favourable variance, as the firm has increased capacity to absorb fixed overheads.

Performance Management Question 8:

Moonstar budgeted to manufacture 2,000 units of a product but made 2,100 units. The standard labour cost per unit was $80 (4 hours at $20 per hour). Employees worked 8,100 hours although they were paid for 8,300 hours. The actual labour cost was $164,000.

What was the labour rate variance for Moonstar?

  1. $4,000 adverse
  2. $2,000 adverse
  3. $2,000 favourable
  4. $4,000 favourable

Answer (Detailed Solution Below)

Option 3 : $2,000 favourable

Performance Management Question 8 Detailed Solution

The correct answer is option 3.

  $  
Actual amount paid 164,000  
Hours paid at standard rate (8,300 × $20) 166,000  
  2,000 Fav

Performance Management Question 9:

A company operates a standard marginal costing system. Last month actual fixed overhead expenditure was 2% below budget and the fixed overhead expenditure variance was $1,250.

What was the actual fixed overhead expenditure for last month?

  1. $61,250
  2. $62,475
  3. $62,500
  4. $63,750

Answer (Detailed Solution Below)

Option 1 : $61,250

Performance Management Question 9 Detailed Solution

The correct answer is A.

Budgeted overhead − actual overhead = $1,250 (this is the fixed overhead expenditure variance)

Budgeted overhead = $1,250 ÷ 0.02 = $62,500 (because actual overhead was $1,250 below budget, and 2% below budget)

Actual overhead = $62,500 − $1,250 = $61,250

Performance Management Question 10:

Jessie Co manufactures a single product. The following estimates of costs have been made for various level of production of the product.

Production (units) 50,000 70,000 100,000
  $000 $000 $000
Variable 3,655 5,117 7,310
Fixed 3,452 3,452 3,452

In addition to the costs listed above, $380,000 of incremental costs will be incurred for every complete 20,000 units produced.

What is the budgeted total production cost if production is budgeted to be 85,000 units?

  1. $9,665,500
  2. $10,045,500
  3. $11,185,500
  4. $11,565,500

Answer (Detailed Solution Below)

Option 3 : $11,185,500

Performance Management Question 10 Detailed Solution

The correct option is option 3.

Variable cost per unit = $7,310,000/100,000 = $73.10 (or calculate as $5,117,000/70,000).

Incremental costs incurred at 85,000 units is 4 increments of 20,000.

Therefore, total production cost = ($73.10 × 85,000) + $3,452,000 + ($380,000 × 4) = $11,185,500

Tutorial note: The question will indicate the number of fixed cost increments. In this case, the cost occurs after 20,000 units are completed, so a production level of 85,000 units incurs four increments.

Get Free Access Now
Hot Links: teen patti gold new version 2024 teen patti master official teen patti comfun card online