In estimation and costing, the estimator should prepare the estimate with complete specifications. Which of the following specifications is NOT in the estimate procedure?

This question was previously asked in
MPPGCL JE Electrical 01 June 2024 Shift 1 Official Paper
View all MPPGCL Junior Engineer Papers >
  1. Scheme of installations
  2. Type of wiring
  3. Quality of materials
  4. Purchase order

Answer (Detailed Solution Below)

Option 4 : Purchase order
Free
MPPGCL JE Electrical Fundamentals Mock Test
1 K Users
20 Questions 20 Marks 24 Mins

Detailed Solution

Download Solution PDF

Explanation:

In estimation and costing, it is crucial for the estimator to prepare the estimate with complete specifications to ensure accuracy and comprehensiveness. Specifications in this context refer to detailed descriptions of materials, workmanship, and methods to be used in the construction of a project. They serve as a guide for the contractor and ensure that the project meets the desired standards and quality. However, not all specifications are part of the estimate procedure. Let's delve into the correct option and analyze the others to understand this better.

Correct Option Analysis:

The correct option is:

Option 4: Purchase order

A purchase order (PO) is a commercial document and first official offer issued by a buyer to a seller, indicating types, quantities, and agreed prices for products or services. It is used to control the purchasing of products and services from external suppliers. While a purchase order is a critical document in the procurement process, it is not typically included in the estimate procedure. The estimate procedure focuses on providing a detailed and accurate forecast of the costs involved in a project, including labor, materials, overheads, and other expenses. The purchase order comes into play after the estimate has been approved and the project has moved into the procurement phase.

In summary, the purchase order is not part of the estimate procedure because it is a document used later in the process to order the materials and services specified in the estimate. It is an action taken post-estimation to acquire the necessary items for the project.

Additional Information

To further understand the analysis, let’s evaluate the other options:

Option 1: Scheme of installations

A scheme of installations refers to the layout and plan of how electrical, plumbing, and other installations will be set up in a project. This is a crucial part of the estimation process as it helps determine the quantity and type of materials needed, the labor required, and the overall cost associated with these installations.

Option 2: Type of wiring

The type of wiring is a specification that describes the kind of electrical wiring to be used in the project. This can include details about the wire gauge, insulation type, and other relevant characteristics. Including the type of wiring in the estimate is essential to ensure that the project meets safety standards and operates efficiently. The cost of different types of wiring can vary significantly, so specifying this detail helps in providing an accurate estimate.

Option 3: Quality of materials

The quality of materials is a specification that details the standards and grades of materials to be used in the project. High-quality materials may be more expensive but could provide better durability and performance. Including this information in the estimate helps ensure that the materials used meet the required standards and that the project will be completed to a high level of quality. This also impacts the overall cost and is therefore an integral part of the estimation process.

Conclusion:

In the context of estimation and costing, the estimator must include specifications such as the scheme of installations, type of wiring, and quality of materials to ensure a comprehensive and accurate estimate. These details directly impact the cost and quality of the project. However, a purchase order is not part of the estimate procedure as it is a document used later to procure the specified materials and services. Understanding the role and timing of each document in the project lifecycle is essential for effective project management and cost control.

Latest MPPGCL Junior Engineer Updates

Last updated on Jul 18, 2025

-> MPPGCL Junior Engineer Notification 2025 has been released for various fields of post (Advt No. 3233).

-> MPPGCL has announced a total of 90 vacancies for Civil, Mechanical, Electrical, and Electronics Engineering (Junior Engineer).

->  Interested candidates can submit their online application form, from 23rd July to 21st August 2025. 

-> MPPGCL Junior Engineer result PDF has been released at the offiical website.

-> The MPPGCL Junior Engineer Exam Date has been announced.

-> The MPPGCL Junior Engineer Notification was released for 284 vacancies.

-> The selection process includes a Computer Based Test and Document Verification.

-> Candidates can check the MPPGCL JE Previous Year Papers which helps to understand the difficulty level of the exam.

Get Free Access Now
Hot Links: all teen patti teen patti joy official teen patti master downloadable content teen patti game - 3patti poker teen patti jodi