Question
Download Solution PDFIn a company assembly line, assembling gear boxes, five workers are assigned tasks who take 10, 8, 6, 9 and 10 minutes respectively. The balance delay for this assembly line is
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFExplanation:
Five boxes:
Cycle time = Max {10, 8, 6, 9, 10}
[Cycle time = 10 minute]
Now,
\({\rm{Life\;efficiency\;}}\left( {{\eta _{line}}} \right) = \frac{{Total\;Work\;Content}}{{No.\;\;of\;Workers\; \times \;Cycle\;Time}}\)
\({\eta _{line}} = \frac{{10\; + \;8 \;+ \;6 \;+ \;9 \;+ \;10}}{{5 \;\times \;10}} = \frac{{43}}{{50}}\)
∴ ηline = 0.86 or 86 %
Balance delay = 100 – 86 %
∴ Balance Delay = 14 %
Last updated on Jul 2, 2025
-> ESE Mains 2025 exam date has been released. As per the schedule, UPSC IES Mains exam 2025 will be conducted on August 10.
-> UPSC ESE result 2025 has been released. Candidates can download the ESE prelims result PDF from here.
-> UPSC ESE admit card 2025 for the prelims exam has been released.
-> The UPSC IES Prelims 2025 will be held on 8th June 2025.
-> The selection process includes a Prelims and a Mains Examination, followed by a Personality Test/Interview.
-> Candidates should attempt the UPSC IES mock tests to increase their efficiency. The UPSC IES previous year papers can be downloaded here.