Crashing is

This question was previously asked in
UPSC ESE 2018 Paper 1
View all UPSC IES Papers >
  1. Abandoning the project
  2. Completing the project with all possible haste
  3. Reduction of duration for a few of the activities
  4. Reducing the cost of the project with all needful modifications

Answer (Detailed Solution Below)

Option 3 : Reduction of duration for a few of the activities
Free
ST 1: UPSC ESE (IES) Civil - Building Materials
6.5 K Users
20 Questions 40 Marks 24 Mins

Detailed Solution

Download Solution PDF

Explanation:

Crashing is the method for shortening the project duration by reducing the time of one or more critical activities to less than their normal time. In crashing if cost increases then time decreases.

F1 S.C 29.7.20 Pallavi  2

Latest UPSC IES Updates

Last updated on Jul 2, 2025

-> ESE Mains 2025 exam date has been released. As per the schedule, UPSC IES Mains exam 2025 will be conducted on August 10. 

-> UPSC ESE result 2025 has been released. Candidates can download the ESE prelims result PDF from here.

->  UPSC ESE admit card 2025 for the prelims exam has been released. 

-> The UPSC IES Prelims 2025 will be held on 8th June 2025.

-> The selection process includes a Prelims and a Mains Examination, followed by a Personality Test/Interview.

-> Candidates should attempt the UPSC IES mock tests to increase their efficiency. The UPSC IES previous year papers can be downloaded here.

More Project Management Questions

More Operations Research Questions

Get Free Access Now
Hot Links: teen patti gold apk download teen patti palace teen patti 51 bonus teen patti master official